ADOSH Program Planned Inspections
Arizona Division of Occupational Safety and Health (ADOSH)
Jessie Atencio, ADOSH Director
Email: [email protected]
Phoenix Office | Tucson Office |
Click for Phone List of ICA Divisions
Click to download this document (PDF)
ARIZONA DIVISION OF OCCUPATIONAL SAFETY AND HEALTH POLICY AND PROCEDURE
Application: | ADOSH Compliance |
Effective Date: | September 21, 2006 |
Policy Number: | 2006-02 |
Reference: | OSHA CPL 02-00-141 |
Subject: | Programmed Construction Inspection Targeting |
TABLE OF CONTENTS
I. PURPOSE
II. SCOPE
III. BACKGROUND
IV. DESCRIPTION OF THE CONSTRUCTION TARGETING PLAN
V. HEALTH CONSTRUCTION INSPECTIONS
VI. RECORDING AND TRACKING
APPENDIX A: C-TARGETING APPLICATION
APPENDIX B: SELECTION CRITERIA OPTIONS
APPENDIX C: SITE SELECTION DESCRIPTION
I. Purpose.
This policy implements ADOSH’s programmed inspection plan for the construction industry. This program does not include general industry worksites.
II. Scope.
This policy applies to planned construction inspections conducted by all ADOSH compliance sections. The policy does not apply to construction inspections conducted in response to an accident, complaint, referral, Local Emphasis Program (LEP) or National Emphasis Program (NEP).
III. Background.
- Due to the mobility of the construction industry, the transitory nature of construction worksites and the fact that construction worksites frequently involve more than one construction employer, inspections are scheduled from a list of construction worksites rather than construction employers. The OSHA contractor will provide to ADOSH a randomly selected list of construction projects from all known covered active projects. This list contains the projected number of sites the ADOSH compliance sections plan on inspecting in the next month.
- OSHA's Construction Inspection Targeting System is required to comply with court decisions on OSHA’s process of selecting worksites for inspection. The system is designed to provide timely information on known active construction projects, including the project's location and the name of the owners, project managers and contractors working on the projects. Since resources limit ADOSH programmed inspections to a small percentage of construction projects started each year, this targeting plan is designed to be a broad-based system that selects projects in a way to establish a presence in the entire construction industry.
- The construction inspection system relies upon a statistical abstract of information available on construction project starts from F.W. Dodge and on estimated construction project durations derived from econometric modeling. The system is designed to get CSHOs on-site at neutrally-selected projects when they are between 30 percent and 60 percent complete, the time when the greatest number of employees and contractors are expected to be on the construction site.
- OSHA’s contractor adds to the Dodge data a time period when each project is active and maintains a file containing all active construction projects. From active construction projects, a randomly selected construction inspection list will be generated for ADOSH office on a monthly basis. This selection is done without employer identifiers to ensure neutrality. The list is based upon:
- Counties located within office boundaries;
- Estimated number of worksites to be inspected during the monthly scheduling period (to be determined by the supervisors);
- The selection criteria are to be determined by the ADOSH Director and/or supervisor based on local conditions. (Note: “Supervisor”, as used in this policy, refers to the office supervisor in charge of managing the construction targeting plan, unless otherwise specified.)
- Counties located within office boundaries;
IV. Description of the Construction Targeting Plan.
- Inspection List Selection Criteria. ADOSH will use the Construction Inspection Targeting Application located at OSHA’s construction targeting website to set specific selection criteria and to access the monthly site inspection lists and associated construction inspection reports (“Dodge” reports). The selection criteria will be determined by ADOSH administration and safety compliance section supervisors. Only ADOSH administration and safety compliance section supervisors will be able to access this website.
- Selection of Projects. This targeting plan is designed to be a broad based system that selects projects in a way to establish a presence in the entire construction industry. The Construction Inspection Targeting Application includes a function that allows supervisors to make minor adjustments by excluding categories of projects from the next monthly random sample of inspection sites. These categories are end-use, construction type, dollar value, number of stories, and type of owner (i.e. Federal government, State, municipality, military or private). ADOSH can use these options to exclude areas of construction that have had a significant amount of focused activity in recent months. For example, if ADOSH is conducting an LEP focusing on bridge construction, the supervisor can use the end-use option to exclude bridge building for the targeting lists generated under this instruction. These options must be used in a manner which retains the program’s overall objective of establishing a presence in the entire construction industry. Supervisors who exercise one or more of the options will also ensure that the generated targeting lists are not limited in a way that compromises the random selection component of the targeting system. If the selected options take away the random selection component, the supervisor must modify the options in a way that generates a randomly selected list.
- Each option within the Construction Inspection Targeting Application is set to a default. On occasion, the director must review these defaults to determine if they are appropriate for the local conditions. If any changes are necessary, the director or supervisor must set the desired deletion or inclusion criteria for the inspection site list or special emphasis site list, respectively. Examples are: excluding or including projects with specific dollar values (less than 1 million dollars); or excluding or selecting projects with specific end-uses (high-rise offices or bridges).
- Another option to facilitate inspection planning is to request projects in a cluster of counties, so that monthly inspections can be focused in selected areas each month. This may result in reducing travel time to remote locations or in saturating counties where an office wants to make ADOSH’s presence felt. However, the supervisor must ensure that all counties with the office’s jurisdiction will be covered within a reasonable time period.
- The supervisor will set the current sample size (i.e., the number of inspection sites that will be provided each month). The office will not receive a list if a sample size of zero is indicated.
- Each option within the Construction Inspection Targeting Application is set to a default. On occasion, the director must review these defaults to determine if they are appropriate for the local conditions. If any changes are necessary, the director or supervisor must set the desired deletion or inclusion criteria for the inspection site list or special emphasis site list, respectively. Examples are: excluding or including projects with specific dollar values (less than 1 million dollars); or excluding or selecting projects with specific end-uses (high-rise offices or bridges).
- Scheduling Cycle. The scheduling period (cycle) for construction inspections is one calendar month. Each month, each office will access its programmed construction inspection list on the Construction Targeting website. Each office will also access the Dodge Reports corresponding to the sites on the inspection list. The inspection list will be dated the following month. It can be used when received and should be completed by the end of the month it is dated. The use of the current list is important because conditions change rapidly and the lists become outdated. The best planning strategy is to receive the required number of sites for the month to ensure that the most current list is always being used.
- All sites on the inspection list must be inspected, and the sites can be scheduled in any order to make efficient use of resources.
- Complaints and referrals must be treated in accordance with the Complaint & Referral Handling policy (ADOSH policy 2006-01).
- ADOSH supervisors are not authorized to make any deletions from that month’s inspection list prior to its completion, except where the supervisor documents that:
- Little or no construction activity at a worksite on the list has begun or construction activity has already been substantially completed before an inspection can be made.
- A worksite has become ineligible for any legitimate reason; e.g., where a substantially complete inspection of the worksite has been conducted as a result of a complaint investigation. (If in doubt whether a worksite has become ineligible, the supervisor is to contact the director.)
- A worksite has been approved for exemption from inspection through participation in the Voluntary Protection Program. (Note: This is not yet a viable reason for ADOSH to delete a site from an inspection list.)
- Little or no construction activity at a worksite on the list has begun or construction activity has already been substantially completed before an inspection can be made.
- Any deletion from a monthly inspection list must be fully documented in accordance with X.F., below.
- If a new list is posted for the following month and it is anticipated that it will not be used at all because of a large number of sites remaining on the current list, the supervisor should reject the list using the Construction Inspection Targeting Application as soon as practicable so that the unused sites may be restored to be eligible for possible selection on the next list.
- If it appears that all sites on the list will have been inspected by the end of the third week of the month, the supervisor may request a supplemental inspection list through the Construction Inspection Targeting Application.
- If a supplemental list is requested and received, it is to be treated in the same manner as a list received at the beginning of the month, i.e., once started, it must be completed.
- The supervisor should consider increasing the sample size if supplemental sites are repeatedly requested. Similarly, if the lists are not routinely completed by the end of the month, consider decreasing the sample size.
- If a supplemental list is requested and received, it is to be treated in the same manner as a list received at the beginning of the month, i.e., once started, it must be completed.
- All sites on the inspection list must be inspected, and the sites can be scheduled in any order to make efficient use of resources.
- Limitation on Frequency of Selection. Normally, no site will be selected for inspection more frequently than once per trimester. Therefore, any project selected for an inspection will be removed from the master file for a period of four months and reentered in the fifth month if it is still active.
- Completion of Inspection List. By the middle of each month, the supervisor shall assess progress in inspecting all sites on the list in order to plan resources for the following month.
- If it appears that not all sites on the list will have been inspected by the end of the month, the supervisor may request a shortened list for the following month by adjusting the sample size through the Construction Inspection Targeting Application.
- Consecutive months' lists may be combined and used concurrently. However, all sites from the first month of a combined list must be inspected before worksites from the second month's list are combined with a third month, except when a site is carried over as described at X.F., below. That is, lists for two consecutive months can be combined to form one combined cycle; but the first month's list must be completed or classified as carryover before the second month's list can be combined with the third month's list, and so on.
- If it appears that not all sites on the list will have been inspected by the end of the month, the supervisor may request a shortened list for the following month by adjusting the sample size through the Construction Inspection Targeting Application.
- Carryovers. Worksites on one inspection list may be carried over to the next cycle only under the following circumstances:
- A worksite may be carried over to the next cycle if it is not operating normally at the time of the inspection because of personnel strikes, environmental conditions or other factors.
- A worksite may be carried over to the next cycle if necessary equipment or personnel with experience and qualifications to perform the inspection are not presently available.
- A worksite may be carried over to the next cycle in the interest of efficient use of resources. Any worksite carried over in this manner may not be carried over a second time.
- A worksite may be carried over to the next cycle if conditions (construction activity at the site) have not changed substantially since a prior inspection.
- A worksite may be carried over to the next cycle if the inspection must be deferred because the employer has requested a full-service comprehensive consultation visit and that visit has been scheduled.
- A worksite may be carried over to the next cycle if the inspection must be deferred because the employer has submitted a VPP application for the site. (Note: This is not yet applicable to ADOSH operations).
- Approval for carrying over a worksite for reasons not listed above must be requested from and approved by the director).
- A worksite may be carried over to the next cycle if it is not operating normally at the time of the inspection because of personnel strikes, environmental conditions or other factors.
- Supervisor Administration of Inspection List. The supervisor is responsible for maintaining documentation necessary to demonstrate that the construction inspection lists have been properly utilized in accordance with the requirements of this policy and that selection criteria are current and appropriate.
- The monthly construction inspection lists must be maintained in the office for a period of two (2) years after completion of the cycle, whether they are used or not.
- New modifications to the offices’ selection criteria must be determined jointly by the director and the designated office supervisor. Such modifications will be effective the month following entry into the computer if they are received by the 23rd of the month. Note: Ongoing changes to the selection criteria, such as sample size, do not need the director’s approval for each monthly change.
- Deletions from a monthly inspection list must be documented by using the “Archive Site” function within the Construction Inspection Targeting Application. The appropriate reason for deletion will be chosen from the drop down menu located in the function.
- The monthly construction inspection lists must be maintained in the office for a period of two (2) years after completion of the cycle, whether they are used or not.
- Compliance Officer Responsibilities. Compliance officers are responsible for ensuring compliance with these policies, to the extent applicable to their work. In general, compliance officers must ensure the following:
- Compliance officers will obtain all programmed planned construction assignments from the programmed construction inspection supervisor (currently Katherine Gosiger - Phoenix and Gilbert Bracamonte – Tucson). A programmed construction inspection will not be conducted at a construction site unless the CSHO has obtained a copy of the Dodge report from the supervisor.
- The CSHO will conduct an inspection of the site prior to the end of the month for which the Dodge is dated.
- If the CSHO does not anticipate being able to conduct an inspection of the site prior to the end of the month, the Dodge shall be returned to the supervisor so that it may be reassigned.
- Upon completion of a site inspection, the CSHO will provide a copy of the Dodge to the scheduling supervisor, noting on it the date of the inspection, the inspection number and the CO ID number
- When completing the Form 1’s for all inspections associated with the site, the CSHO will enter in Field #42 (Optional Information) the Type, ID and PID, as specified in XII below.
- Compliance officers will obtain all programmed planned construction assignments from the programmed construction inspection supervisor (currently Katherine Gosiger - Phoenix and Gilbert Bracamonte – Tucson). A programmed construction inspection will not be conducted at a construction site unless the CSHO has obtained a copy of the Dodge report from the supervisor.
V.Health Construction Inspections.
No separate scheduling method is applied for programmed construction health inspections. Rather, the supervisor is to determine which construction inspections are to be conducted as a joint inspection where serious health hazards are likely to exist at the site. A local emphasis plan may be submitted and approved for scheduling health construction inspections.
The Project Identification Number (PID) must be recorded into the IMIS for each construction project inspected under this policy. The PID is entered on all of the ADOSH 1’s generated for the general contractor and the subcontractors at the worksite. The PID number is the unique six-digit number that identifies each project on the monthly programmed construction inspection list provided through the Construction Inspection Targeting Application. The PID is coded as follows in Item 42, Optional Information of the OSHA-1 Form:
Type | ID | Value |
N | 06 | PID (six-digit PID Number) |
Note: The PID is also referred to as the Dodge Number. |
APPENDIX A: C-Targeting Application
What is the Construction Inspection Targeting Application?
The OSHA Construction Inspection Targeting Application is an efficient, electronic way to provide authorized personnel detailed information on construction projects in your area that have been selected for a programmed inspection and projects that meet criteria established for any construction special emphasis programs. The application consolidates and facilitates timely access to information on the selected project sites in a secure database that authorized personnel can access via the Internet anywhere and at anytime.
What functions are available in Construction Targeting?
The following functions are available:
- View each of the five lists (Inspection Sites, Supplemental Sites, Special Emphasis Sites, Early Warning Sites, and Archived Sites).
- View detailed data on a project/site, multiple sites, or all sites from a list.
- View or change deletion criteria for the Inspection Site list.
- Change the number of inspection sites that are requested each month.
- Request additional supplemental inspection sites to inspect.
- View or change selection criteria for the Special Emphasis Site list.
- Print lists and detailed data on a project/site, multiple sites, or all sites from a list.
- Archive a site that has been inspected, completed prior to inspection, or canceled.
- Re-sort a list based on any of the data in the list.
- Search the database using specified data fields.
What worksites do I have access to?
OSHA Area Offices, Regional Offices, and State Plan States can only view project sites that have been selected in their area. Nonauthorized users will not be able to see any of this information.
How do I archive inspected sites?
When an inspection is completed for a project that is on the Inspection Site List, the Supplemental Site List, or the Special Emphasis Site list, enter in the IMIS Activity Number (OSH1) of the inspection in the designated field on the detailed display for the site. This removes the project site from the Inspection Site List to the Archives.
If a project was completed prior to an inspection, enter the word “completed” into the activity number field. If a project was canceled, enter the word “canceled” into the activity number field. Entering “completed” or “canceled” into the activity number field moves the project site to the Archives. Early Warning sites are automatically removed from the database each month when the new sites are posted to the application. Project sites will stay in the archives indefinitely. For large projects, inspection lists may include what appear to be duplicate entries for the same site. This occurs when a separate bidding process was used for different portions of a project. What options does the Area Office/State Plan State have to focus the inspection lists on particular categories of construction? The construction inspection system is designed to be responsive to the needs of Area Offices/State Plan States. Options are built in to help target the different categories (end-use, type, dollar value, number of stories, and type of owner (i.e. Federal government, State, municipality, military or private)) of construction projects. An Area Office/State Plan State can specify or update criteria to exclude categories of projects from the monthly random sample of inspection sites or obtain all sites meeting specified criteria for special emphasis programs by clicking on the Options tab. Click on 'view or change' criteria and then on 'Update'. Use the check boxes to indicate the desired deletion or inclusion criteria for the inspection site list or special emphasis site list, respectively. Examples are: excluding or including projects with specific dollar values (less than 1 million dollars); or excluding or selecting projects with specific end-uses (high-rise offices or bridges). The deletion and inclusion criteria focus inspection lists on particular categories of construction projects. Another option to facilitate inspection planning is to request projects in a cluster of counties within an Area Office/State Plan State jurisdiction, so that monthly inspections can be focused in selected areas each month. This may result in reducing travel time to remote locations or in saturating counties where a jurisdiction wants to make OSHA's presence felt. Indicate this choice by selecting 'other' and typing a description of desired county rotation in the text box. How can the size of the monthly inspection site list be managed? The Options page indicates the current sample size; i.e., the number of inspection sites that have been requested for a month. Click on 'change' to increase or decrease that sample size. The Office will not receive a list if a sample size of zero is indicated.
If the Office has inspected all listed sites before the end of the month, the user can click on 'request' under Supplemental Sites to obtain more sites. An Office should consider increasing the sample size if it repeatedly has to request supplemental sites. Similarly, if the Office is not completing its lists by the end of the month, it should consider decreasing the sample size.
When do I have to make changes for the next month's list?
Supplemental lists can be requested any time during the month. The request for additional sites will be filled and posted to the database as soon as possible. Changes to sample size and deletion criteria for the inspection site list and changes to selection criteria for the special emphasis site list must be made by the 23rd of the month (or first business day after a weekend or holiday) to be processed for the next month’s list.
.APPENDIX B: Selection Criteria Options
Sample Size
The sample size is the number of construction project sites requested each month. The sample size can be changed as frequently as needed, based on an office's current workload.
Request Supplemental Sites
If an office completes all of its listed inspections, authorized personnel may request additional supplemental sites to inspect.
Request Special Emphasis Sites
An office may request a list of construction project sites for its own construction targeting initiatives. Note that these targeting initiatives need to be approved by the National Office.
Inspection Site Deletion Criteria
The Inspection Site Deletion Criteria are used to exclude categories or types of construction project sites from being selected for inspection. These criteria can be viewed or changed to meet the needs of the office.
Special Emphasis Selection Criteria
The Special Emphasis Selection Criteria are used to select categories or types of construction project sites for your office's construction targeting initiatives. These criteria can be viewed or changed to meet the needs of the office.APPENDIX C: Site Selection Description
What is the legal basis for the OSHA Construction Inspection Targeting System?
Due to several court challenges to the worksite selection process for inspections, OSHA developed the current Federal programmed construction inspection system. The project selection process which drives the system meets the legal requirement that projects be selected pursuant to an administrative plan containing specific neutral criteria. Projects are randomly selected from a file representing the universe of active construction projects that contains no contractor identifiers.
In addition, the Office of Inspector General (OIG) requires documentation of the project selection procedures for construction inspections that Area Offices follow. However, since preparation and maintenance of such documentation would be impracticable and unduly burdensome on Area Offices, the current system serves as the documentation.
How are sites selected?
A computer-based methodology is used to select projects for inspection on a random, statistical basis. Selected sites represent a broad range of construction projects: residential (excluding single-family housing); nonresidential buildings, such as commercial, manufacturing, transport, industrial, educational, leisure, & public buildings; heavy construction, such as cogenerators, nuclear power, sewage treatment, communications, shoreline maintenance; and highway and highway-related construction, including bridges, tunnels.
Each month, F.W. Dodge provides CIRPC with the names of projects that have entered the start stage (about 18,300 projects per month), based upon the date of the award of a general contract or the date when project decisionmakers state that "work is to start on a particular date". Using a sophisticated construction duration model that factors in the start date of the project, estimated duration of the project, type of construction project, dollar value, type of owner (i.e. Federal government, State, municipality, military or private), number of stories, and a seasonal adjustment, projects are identified that are estimated to be at some stage of construction, i.e., active. Accurate start date information is critical to estimates of when projects will be prime for inspection (30 percent to 60 percent complete).
Projects are randomly selected to obtain the number requested by the Area Office/State Plan State. Initially, only projects $950,000 and more which are estimated to be between 30 percent and 60 percent complete are considered for selection. If the requested quota cannot be met using these criteria, the “percent complete” criterion is expanded to 25 percent to 65 percent and then to 25 percent to 70 percent complete, if necessary. If more projects are still required, the value criterion is lowered to $500,000 (30 percent - 60 percent complete). The final step to meet a sufficient number ofprojects reduces the value criterion to $250,000 with a 30 to 60 percent completion criterion.
Projects are identified by project identification numbers (PID). Once selected, the PIDs are used to order an OSHA Construction Report for each project from F.W. Dodge. Each report contains the following information: project identification number - unique to each project; project title; project address (or site location information when address not applicable); project owner's name, business address, & telephone number; estimated contract value; estimated square footage of buildings; number of units (on residential projects); number of buildings; estimated construction start date; type of ownership (i.e. Federal government, State, municipality, military or private).
How accurate are the data on the projects?
The information source on construction projects for the construction inspection targeting system is F.W. Dodge, Inc., the most extensive construction news gathering operation in the world. Dodge employs 400 full-time reporters and more than 1,000 correspondents to collect information from a large network of news sources, including permit offices. After the information is collected, individual project reports are created. To ensure coverage of as much construction activity as possible, Dodge maintains 100 branch offices around the country. Reporters make personal visits and phone calls, daily, to about 55,000 private firms, permit offices, municipal, state, and government offices to obtain information pertaining to approval, design, development, and construction of all types of construction projects over $50,000, including new construction, additions and alterations. Coverage is not restricted to bid contracts but includes negotiated contracts and major force account work (use of owner's employees rather than contractor's) as well.
F.W. Dodge files represent the best available universe of active construction projects. An independent study funded by OSHA found that the Dodge database covers over 90 percent of the universe of all construction projects over $50,000, excluding single-family housing. Farm construction and small force account projects were areas with less complete coverage.
In an ideal world, all construction projects would be known, each project would start in the month it was planned to start, each project would remain active the number of months estimated by econometric models, and each project would proceed along an orderly path of construction operations that would accurately estimate in advance the day that excavation, steel erection or landscaping, would begin and end.
However, actual construction activity is less orderly. Construction plans are constantly changing; project duration is not available from construction permits or other sources; each project is unique; the scheduling of construction operations and their duration differ from project to project, even of the same type, and schedules are rarely met. Construction schedules for similar end-use projects, such as office buildings, highways, bridges or schools of equal contract value may vary dramatically in duration due todifferent design features, site conditions and the owner's cost of delayed occupancy (use). Even assuming that scheduled duration of projects were available from owners or contractors, project duration errors would still exist because of schedule interruptions due to such things as litigation among contractors/owners, industrial relations disputes, financial problems, or unforeseen construction problems, which are all common events on construction projects. Given the uncertainties, some of the projects expected to be 30 percent to 60 percent complete will be in an earlier stage (or not even started) or at a later stage (or even completed). On the other hand, the systematic process of identifying projects and estimating their status using the best available data increases the likelihood that inspections will occur at all stages of construction.
What are Early Warning Sites?
In addition to the random selections of project sites for inspection each month, high-value projects at the start stage (month the project is planned to start) are identified. The purpose of the Early Warning Site (EWS) List is to alert Area Offices/State Plan States to the initiation of major construction projects, so that their progress might be followed to ensure a timely inspection of specific phases. Each Early Warning Site will appear on the Inspection Site List for the month the project is estimated to be 30 percent complete.
The value threshold to qualify as an Early Warning Site varies by Area Office/State Plan State, ranging from $5 million to $20 million, depending upon the five-year historical pattern of project values in the respective area office jurisdiction.